Aug-08
Aug-09
APOLLO MIDDLE 273,600.000 KWH 256,560.000 KWH
ARTHUR ASHE MIDDLE 323,200.000 KWH 284,800.000 KWH
ATLANTIC VOC CENTER 589,875.000 KWH 584,562.000 KWH
ATLANTIC WEST ELEM 147,480.000 KWH 120,360.000 KWH
ATTUCKS MIDDLE 304,080.000 KWH 305,776.000 KWH
BAIR MIDDLE 204,960.000 KWH 208,320.000 KWH
BANYAN ELEM 121,560.000 KWH 129,120.000 KWH
BAYVIEW ELEM 133,200.000 KWH 104,880.000 KWH
BECON 229,640.000 KWH 170,400.000 KWH
BENNETT ELEM 122,160.000 KWH 78,000.000 KWH
BETHUNE ELEM 235,920.000 KWH 213,960.000 KWH
BOULEVARD HEIGHTS ELEM 158,640.000 KWH 100,080.000 KWH
BOYD ANDERSON HIGH 496,512.000 KWH 519,416.000 KWH
BRIGHT HORIZONS CTR 166,560.000 KWH 135,360.000 KWH
BROADVIEW ELEM 157,372.000 KWH 145,403.000 KWH
BROWARD ESTATES ELEM 137,654.000 KWH 130,275.000 KWH
BROWARD FIRE ACADEMY 31,966.000 KWH 38,458.000 KWH
CASTLE HILL ELEM 150,360.000 KWH 136,320.000 KWH
CENTRAL PARK ELEM 147,720.000 KWH 78,720.000 KWH
CHALLENGER ELEMENTARY 170,760.000 KWH 152,280.000 KWH
CHAPEL TRAIL ELEM 227,113.000 KWH 171,674.000 KWH
CHARLES DREW ELEM 111,000.000 KWH 119,160.000 KWH
COCONUT CREEK ELEM 76,683.000 KWH 65,930.000 KWH
COCONUT CREEK HIGH 330,776.000 KWH 247,754.000 KWH
COCONUT PALM ELEMENTARY 157,920.000 KWH 115,440.000 KWH
COLBERT ELEM 124,320.000 KWH 176,880.000 KWH
COLLINS ELEM 87,360.000 KWH 80,640.000 KWH
COMMUNITY SCHOOL NORTH 30,720.000 KWH 29,520.000 KWH
COMMUNITY SCHOOL SOUTH .000 KWH 12,580.000 KWH
COOPER CITY COMM 4,292.000 KWH 8,164.000 KWH
COOPER CITY ELEM 152,160.000 KWH 46,560.000 KWH
COOPER CITY HIGH 581,347.000 KWH 520,913.000 KWH
CORAL COVE ELEMENTARY 123,120.000 KWH 99,840.000 KWH
CORAL GLADES HIGH 504,960.000 KWH 501,360.000 KWH
CORAL PARK ELEM 155,640.000 KWH 129,960.000 KWH
CORAL SPRINGS ELEM 127,440.000 KWH 102,000.000 KWH
CORAL SPRINGS HIGH 439,724.000 KWH 440,664.000 KWH
CORAL SPRINGS MIDDLE 254,040.000 KWH 219,240.000 KWH
COUNTRY HILLS ELEM 152,760.000 KWH 168,960.000 KWH
COUNTRY ISLES ELEM 177,360.000 KWH 203,400.000 KWH
CRESTHAVEN ELEM 131,640.000 KWH 126,240.000 KWH
CROISSANT PARK ELEM 106,371.000 KWH 106,911.000 KWH
CROSS CREEK 75,360.000 KWH 74,340.000 KWH
CRYSTAL LAKE COMM SCHOOL 10,514.000 KWH 10,801.000 KWH
CRYSTAL LAKE MIDDLE 273,118.000 KWH 283,665.000 KWH
CYPRESS BAY HIGH 489,200.000 KWH 446,400.000 KWH
CYPRESS BAY HIGH ANNEX 68,640.000 KWH 54,000.000 KWH
CYPRESS ELEM 116,640.000 KWH 111,120.000 KWH
CYPRESS RUN ALTERNATIVE 85,775.000 KWH 78,283.000 KWH
DANIA ELEM 140,315.000 KWH 139,431.000 KWH
DAVE THOMAS ED CENTER (WEST) 120,720.000 KWH 82,560.000 KWH
DAVE THOMAS EDUCATION CENTER 47,693.000 KWH 46,695.000 KWH
DAVIE ELEM 126,555.000 KWH 100,126.000 KWH
DEERFIELD BEACH ELEM 217,080.000 KWH 174,491.000 KWH
DEERFIELD BEACH HIGH 467,663.000 KWH 430,161.000 KWH
DEERFIELD BEACH MID 302,489.000 KWH 335,752.000 KWH
DEERFIELD PARK ELEM 136,200.000 KWH 149,040.000 KWH
DILLARD ELEM 148,680.000 KWH 112,320.000 KWH
DILLARD HIGH COMM 5,491.000 KWH .000 KWH
DILLARD HIGH SCHOOL 632,556.000 KWH 651,777.000 KWH
DISCOVERY ELEMENTARY .000 KWH 248,880.000 KWH
DOLPHIN BAY ELEMENTARY 117,360.000 KWH 102,480.000 KWH
DREW RESOURCE CTR 74,435.000 KWH 103,991.000 KWH
DRIFTWOOD ELEM 83,362.000 KWH 88,660.000 KWH
DRIFTWOOD MIDDLE 464,813.000 KWH 342,245.000 KWH
EAGLE POINT ELEM 276,120.000 KWH 245,880.000 KWH
EAGLE RIDGE ELEM 162,360.000 KWH 133,680.000 KWH
ECIA SPECIAL PROGRAMS 35,183.000 KWH 33,255.000 KWH
EDGEWOOD CENTER 51,736.000 KWH 76,456.000 KWH
ELY HIGH 790,723.000 KWH 653,760.000 KWH
EMBASSY CREEK ELEM 94,680.000 KWH 107,280.000 KWH
ENDEAVOR LEARNING CENTER 82,800.000 KWH 69,480.000 KWH
EVERGLADES ELEMENTARY 255,627.000 KWH 149,324.000 KWH
EVERGLADES HIGH 614,040.000 KWH 445,080.000 KWH
FAIRWAY ELEM 173,760.000 KWH 160,680.000 KWH
FALCON COVE MIDDLE 425,866.000 KWH 286,797.000 KWH
FLAMINGO ELEM 160,648.000 KWH 111,448.000 KWH
FLANAGAN HIGH 534,799.000 KWH 515,741.000 KWH
FLORANADA ELEM 194,856.000 KWH 157,656.000 KWH
FOREST GLEN MIDDLE 196,560.000 KWH 182,605.000 KWH
FOREST HILLS ELEM 126,960.000 KWH 139,320.000 KWH
FORT LAUDERDALE HIGH 531,054.000 KWH 387,589.000 KWH
FOX TRAIL ELEMENTARY 148,320.000 KWH 135,600.000 KWH
GATOR RUN ELEMENTARY 290,280.000 KWH 192,720.000 KWH
GLADES MIDDLE 284,800.000 KWH 265,200.000 KWH
GRIFFIN ELEM 95,880.000 KWH 83,280.000 KWH
GULFSTREAM MIDDLE SCHOOL 96,600.000 KWH 110,760.000 KWH
HALLANDALE ADULT CENTER 200,789.000 KWH 197,505.000 KWH
HALLANDALE ELEM 163,440.000 KWH 160,560.000 KWH
HALLANDALE HIGH 295,600.000 KWH 347,735.000 KWH
HARBORDALE ELEM 81,048.000 KWH 77,688.000 KWH
HAWKES BLUFF ELEM 181,461.000 KWH 136,323.000 KWH
HERON HEIGHTS ELEMENTARY .000 KWH 176,400.000 KWH
HOLLYWOOD CENTRAL AUDITORIUM 41,640.000 KWH 43,200.000 KWH
HOLLYWOOD CENTRAL ELEM 103,200.000 KWH 107,880.000 KWH
HOLLYWOOD HILLS COMMUNITY 3,635.000 KWH 4,691.000 KWH
HOLLYWOOD HILLS ELEMENTARY 168,840.000 KWH 181,440.000 KWH
HOLLYWOOD HILLS HIGH 404,246.000 KWH 409,310.000 KWH
HOLLYWOOD PARK ELEM 100,800.000 KWH 67,200.000 KWH
HORIZON ELEM 114,120.000 KWH 107,760.000 KWH
HORTT ADMIN SITE 74,206.000 KWH 60,476.000 KWH
INDIAN RIDGE MIDDLE 266,196.000 KWH 240,188.000 KWH
INDIAN TRACE ELEM 152,400.000 KWH 146,160.000 KWH
JAMES HUNT ELEMENTARY 129,924.000 KWH 111,600.000 KWH
KATHLEEN WRIGHT ADMIN 460,296.000 KWH 394,978.000 KWH
LAKE FOREST ELEM 233,160.000 KWH 171,960.000 KWH
LAKESIDE ELEMENTARY 132,000.000 KWH 102,960.000 KWH
LANIER JAMES CENTER 81,600.000 KWH 72,240.000 KWH
LARKDALE ELEM 120,341.000 KWH 97,543.000 KWH
LAUDERDALE LAKES MIDDLE 207,840.000 KWH 205,106.000 KWH
LAUDERDALE MANORS ELEM 250,320.000 KWH 141,840.000 KWH
LAUDERHILL MIDDLE 183,600.000 KWH 164,760.000 KWH
LAUDERHILL MIDDLE/COMM 4,326.000 KWH 5,408.000 KWH
LAUDERHILL PT ELEM 153,840.000 KWH 139,320.000 KWH
LIBERTY ELEMENTARY 171,120.000 KWH 136,320.000 KWH
LLOYD ESTATES ELEM 144,480.000 KWH 144,960.000 KWH
LOCKHART STADIUM 90,624.000 KWH 80,482.000 KWH
LYONS CREEK MIDDLE 336,000.000 KWH 362,400.000 KWH
MANATEE BAY ELEMENTARY 164,386.000 KWH 145,722.000 KWH
MAPLEWOOD ELEM 139,320.000 KWH 127,200.000 KWH
MARGATE ELEM 186,120.000 KWH 154,920.000 KWH
MARGATE MIDDLE 298,940.000 KWH 223,004.000 KWH
MARKHAM ELEM 124,571.000 KWH 101,107.000 KWH
MARTIN LUTHER KING ELEM 176,998.000 KWH 174,480.000 KWH
MCARTHUR HIGH 451,772.000 KWH 417,122.000 KWH
MCFATTER VO TECH 330,720.000 KWH 310,320.000 KWH
MCNAB ELEMENTARY 156,960.000 KWH 147,626.000 KWH
MCNICOL MIDDLE 289,200.000 KWH 283,680.000 KWH
MEADOWBROOK ELEM 175,993.000 KWH 171,360.000 KWH
MILLENNIUM MIDDLE 312,000.000 KWH 316,320.000 KWH
MIRAMAR ELEM 160,200.000 KWH 154,680.000 KWH
MIRAMAR HIGH 406,061.000 KWH 333,205.000 KWH
MIRROR LAKE ELEM 84,480.000 KWH 88,320.000 KWH
MONARCH HIGH 406,000.000 KWH 310,400.000 KWH
MORROW ELEM 106,800.000 KWH 77,880.000 KWH
MULTICULTURAL CENTER 26,760.000 KWH 12,000.000 KWH
N ANDREWS GARDENS ELEM 214,104.000 KWH 161,544.000 KWH
NEW RENAISSANCE MIDDLE 255,467.000 KWH 195,494.000 KWH
NEW RIVER CIRCLE SITE 179,784.000 KWH 38,304.000 KWH
NEW RIVER MIDDLE SCHOOL 287,280.000 KWH 205,560.000 KWH
NOB HILL ELEM 138,960.000 KWH 104,520.000 KWH
NORCREST ELEM 218,881.000 KWH 170,149.000 KWH
NORTH AREA MAINT/WHSE 38,160.000 KWH 35,700.000 KWH
NORTH BUS PARKING LOT 80,684.000 KWH 82,933.000 KWH
NORTH CENTRAL SUPERINTENDENT 108,300.000 KWH 86,760.000 KWH
NORTH FORK ELEM 181,080.000 KWH 130,080.000 KWH
NORTH LAUDERDALE ELEM 103,200.000 KWH 85,680.000 KWH
NORTH SIDE ELEMENTARY 123,000.000 KWH 111,000.000 KWH
NORTHEAST HIGH 332,753.000 KWH 312,910.000 KWH
NOVA BLANCHE FORMAN/EISENHOWER ELEM 214,800.000 KWH 212,000.000 KWH
NOVA EISENHOWER ELEMENTARY 9,118.000 KWH 8,539.000 KWH
NOVA HIGH 4,773.000 KWH 35,205.000 KWH
NOVA HIGH - MECH PLANT 627,200.000 KWH 604,800.000 KWH
OAKLAND PARK ELEM 177,000.000 KWH 155,280.000 KWH
OAKRIDGE ELEM 141,419.000 KWH 117,518.000 KWH
OFF CAMPUS ALTERNATIVE CENTER .000 KWH 26.000 KWH
OLSEN MIDDLE 182,640.000 KWH 214,320.000 KWH
OLSEN MIDDLE ANNEX 143,720.000 KWH 179,480.000 KWH
ORANGE BROOK ELEM 135,840.000 KWH 132,480.000 KWH
ORIOLE ELEM 124,800.000 KWH 126,240.000 KWH
PALM COVE ELEM 130,200.000 KWH 121,680.000 KWH
PALMVIEW ELEM 143,760.000 KWH 135,960.000 KWH
PANTHER RUN ELEM 103,320.000 KWH 102,960.000 KWH
PARK LAKES ELEMENTARY 213,840.000 KWH 204,480.000 KWH
PARK LAKES ELEMENTARY ANNEX 19,528.000 KWH 52,168.000 KWH
PARK RIDGE ELEM 138,720.000 KWH 115,440.000 KWH
PARK SPRINGS ELEM 162,960.000 KWH 138,000.000 KWH
PARK TRAILS ELEMENTARY 211,560.000 KWH 171,600.000 KWH
PARKSIDE ELEMENTARY 162,960.000 KWH 151,440.000 KWH
PARKWAY MIDDLE 400,782.000 KWH 351,916.000 KWH
PASADENA LAKES ELEM 133,944.000 KWH 144,178.000 KWH
PEMBROKE LAKES ELEM 137,220.000 KWH 85,320.000 KWH
PEMBROKE PINES ELEM 138,903.000 KWH 134,351.000 KWH
PERRY ELEM 146,811.000 KWH 112,049.000 KWH
PERRY MIDDLE 277,440.000 KWH 219,120.000 KWH
PETERS ELEM 149,901.000 KWH 98,054.000 KWH
PHYSICAL PLANT OPERATIONS 116,701.000 KWH 112,286.000 KWH
PINE RIDGE CTR 93,360.000 KWH 88,080.000 KWH
PINES LAKES ELEM 135,000.000 KWH 162,960.000 KWH
PINES MIDDLE 206,968.000 KWH 196,168.000 KWH
PINEWOOD ELEM 162,240.000 KWH 161,640.000 KWH
PIONEER MIDDLE 176,542.000 KWH 187,499.000 KWH
PIONEER MIDDLE ANNEX 33,480.000 KWH 34,140.000 KWH
PIPER HIGH 480,294.000 KWH 505,654.000 KWH
PLANTATION ELEM 141,704.000 KWH 143,866.000 KWH
PLANTATION HIGH 381,368.000 KWH 337,389.000 KWH
PLANTATION MIDDLE 204,106.000 KWH 134,555.000 KWH
PLANTATION PARK ELEM 80,705.000 KWH 78,932.000 KWH
POMPANO BEACH ELEM 130,800.000 KWH 125,760.000 KWH
POMPANO BEACH HIGH 368,755.000 KWH 333,801.000 KWH
POMPANO BEACH MIDDLE 289,488.000 KWH 286,968.000 KWH
PORTABLE AT PINES 103,459.000 KWH 111,254.000 KWH
PPO ZONE 2 - LEASED 23,135.000 KWH 26,287.000 KWH
QUIET WATERS ELEM 179,820.000 KWH 215,640.000 KWH
RAMBLEWOOD ELEM 130,320.000 KWH 98,400.000 KWH
RAMBLEWOOD MIDDLE 285,840.000 KWH 223,264.000 KWH
RICKARDS MIDDLE 182,793.000 KWH 189,325.000 KWH
RIVERGLADES ELEM 118,440.000 KWH 105,360.000 KWH
RIVERLAND ELEM 94,200.000 KWH 88,200.000 KWH
RIVERSIDE ELEM 169,320.000 KWH 158,640.000 KWH
ROCK ISLAND ADMIN 97,992.000 KWH 88,032.000 KWH
ROYAL PALM ELEMENTARY 184,466.000 KWH 181,743.000 KWH
SANDERS PARK ELEM 120,000.000 KWH 109,600.000 KWH
SANDPIPER ELEM 163,200.000 KWH 176,640.000 KWH
SAWGRASS ELEM 131,280.000 KWH 124,560.000 KWH
SAWGRASS SPRINGS MIDDLE 241,200.000 KWH 237,000.000 KWH
SEA CASTLE ELEM 168,480.000 KWH 129,360.000 KWH
SEAGULL SCHOOL 127,511.000 KWH 110,257.000 KWH
SEMINOLE MIDDLE 273,120.000 KWH 264,840.000 KWH
SHERIDAN HILLS ELEM 95,766.000 KWH 85,094.000 KWH
SHERIDAN PARK ELEM 155,040.000 KWH 108,720.000 KWH
SHERIDAN VOCATIONAL 402,240.000 KWH 343,920.000 KWH
SILVER LAKES ELEMENTARY 122,880.000 KWH 113,880.000 KWH
SILVER LAKES MIDDLE 161,880.000 KWH 164,520.000 KWH
SILVER PALMS ELEM 156,120.000 KWH 171,240.000 KWH
SILVER RIDGE ELEM 191,040.000 KWH 194,160.000 KWH
SILVER SHORES ELEMENTARY 140,040.000 KWH 129,360.000 KWH
SILVER TRAIL MIDDLE 255,600.000 KWH 228,480.000 KWH
SOUTH AREA BUS PARKING 40,466.000 KWH 41,461.000 KWH
SOUTH AREA MAINTENANCE 24,045.000 KWH 24,890.000 KWH
SOUTH BROWARD HIGH 517,094.000 KWH 474,802.000 KWH
SOUTH PLANTATION HIGH 438,134.000 KWH 364,682.000 KWH
Southwest Area Bus Complex 40,485.000 KWH 43,305.000 KWH
STEPHEN FOSTER ELEM 202,285.000 KWH 151,882.000 KWH
STIRLING ELEM 128,160.000 KWH 119,040.000 KWH
STONEMAN DOUGLAS HIGH 494,800.000 KWH 463,200.000 KWH
STRANAHAN HIGH 485,761.000 KWH 382,930.000 KWH
SUNLAND PARK ELEM 99,360.000 KWH 71,520.000 KWH
SUNRISE MIDDLE 295,933.000 KWH 248,412.000 KWH
SUNSET LAKES ELEMENTARY 122,280.000 KWH 139,080.000 KWH
SUNSET SCHOOL 140,352.000 KWH 128,832.000 KWH
SUNSHINE ELEMENTARY 136,024.000 KWH 136,512.000 KWH
TAMARAC ELEM 164,640.000 KWH 152,160.000 KWH
TARAVELLA HIGH 488,867.000 KWH 457,237.000 KWH
TECHNOLOGY AND SUPPORT SERVICE 390,000.000 KWH 364,320.000 KWH
TEDDER ELEMENTARY SCHOOL 175,150.000 KWH 179,653.000 KWH
TEQUESTA TRACE MIDDLE 210,600.000 KWH 189,840.000 KWH
THE QUEST CENTER 111,840.000 KWH 92,040.000 KWH
THURGOOD MARSHALL ELEM 99,504.000 KWH 92,544.000 KWH
TRADEWINDS ELEM 214,560.000 KWH 184,560.000 KWH
Transportation Services Annex 13,320.000 KWH 11,760.000 KWH
TROPICAL ELEM 153,665.000 KWH 137,758.000 KWH
TWIN LAKES ADMIN 67,200.000 KWH 75,840.000 KWH
TWIN LAKES ANNEX/NEW WHSE 3,555.000 KWH 2,364.000 KWH
TWIN LAKES COMPLEX 121,222.000 KWH 122,273.000 KWH
VEHICLE MAINTENANCE 99,120.000 KWH 87,600.000 KWH
VILLAGE ELEM 182,700.000 KWH 143,940.000 KWH
VIRGINIA YOUNG ELEM 106,680.000 KWH 107,280.000 KWH
WALKER ELEM 195,746.000 KWH 188,903.000 KWH
WALTER C YOUNG MIDDLE 492,166.000 KWH 411,171.000 KWH
WATKINS ELEM 186,480.000 KWH 189,600.000 KWH
WELLEBY ELEM 108,000.000 KWH 107,880.000 KWH
WEST BROWARD HIG/LLL 396,800.000 KWH 442,400.000 KWH
WEST CENTRAL BUS COMPLEX 67,158.000 KWH 62,911.000 KWH
WEST HOLLYWOOD ELEM 99,120.000 KWH 84,960.000 KWH
WESTCHESTER ELEMENTARY 132,551.000 KWH 176,212.000 KWH
WESTERN HIGH 479,732.000 KWH 553,164.000 KWH
WESTGLADES MIDDLE 268,080.000 KWH 283,920.000 KWH
WESTPINE MIDDLE 159,480.000 KWH 169,320.000 KWH
WESTWOOD HEIGHTS ELEM 171,564.000 KWH 109,926.000 KWH
WHIDDON-ROGERS ED CENTER 148,400.000 KWH 152,400.000 KWH
WHISPERING PINES 91,560.000 KWH 100,200.000 KWH
WILLIAM DANDY MIDDLE 185,880.000 KWH 169,080.000 KWH
WILTON MANORS ELEM 161,520.000 KWH 146,700.000 KWH
WINGATE OAKS CTR 122,520.000 KWH 98,760.000 KWH
WINSTON PARK ELEM 168,240.000 KWH 134,400.000 KWH